谈岩土控制变形分析法 被引量:2

Discussion on deformation analysis method of rock control
在线阅读 下载PDF
导出
摘要 介绍了新意法的核心思想、工作流程、施工关键技术,并与新奥法进行对比,对其优点进行了总结,同时引用锦屏引水洞室软弱大变形洞段施工经验予以验证,旨在为"新意法"推广应用提供指导。 The paper introduces the core idea, working procedure, critical construction technology of new Italian tunneling method, compares it with new Austrian tunneling method, and summarizes its advantages. Simultaneously, it makes a proof by introducing the weak deformation hole construction experience of Jinping water hole, with a view to provide guidance for the application and proniotion of "new Italian tunneling method".
出处 《山西建筑》 2012年第17期75-77,共3页 Shanxi Architecture
关键词 新意法 隧道工程 超前核心土 施工技术 new Italian tunneling method, tunnel engineering, pre-core soil, construction technology
  • 相关文献

参考文献4

二级参考文献14

  • 1王正松,孙铁成,高波.全断面预加固隧道施工工法(新意法)[J].铁道标准设计,2007,27(z1):170-173. 被引量:24
  • 2高新强,仇文革,关宝树.新建铁路隧道动态设计系统的构思[J].铁道标准设计,2004,24(8):44-47. 被引量:9
  • 3孙兆远,罗琼,耿伟,张念.铁路客运专线大断面隧道开挖方法选择[J].隧道建设,2007,27(A01):9-15. 被引量:18
  • 4[2]Pietro Lunardi.The design and construction of tunnels using the approaeh based on the analysis of controlled deformation in rocks and soils[J].Tunnels & Tuunding International ADECO-RS Approach,2000(5):3-30.
  • 5[3]P.Lunardi,R.Bindi.The evolution of reinforcement of the advance core using fibre glass elements for short and long term stability of tunnels under difficult sliess-straiu conditions:design,technologies and operating methods[C]//Progress in Tunnelling after 2000:Proceedings of the AITES-ITA 2001 World Tunnel Congress Milan-Italy 10th-13th June 2001.Volume Ⅱ.Bologna:PATRON EDITORE,2001:309-322.
  • 6[4]P.Lunardi.The ADECO-RS Approach in the design and construction of the Rome to Naples high speed railway line:a comparison between final design specifications,conshruction design and"as-built"[C]//Progress in Tunnelling after 2000:Proceedings of the AITES-ITA 2001 World Tunnel Congress Milan-Italy 10th-13th June 2001.Vdume Ⅲ.Bologna:PATRON EDITORE,2001:329-340.
  • 7[5]P.Lunardi,C.Silva,A.Focracci.The Bologna to Florence high speed railway line:92km through the Appennines[C]//Progress in Tunnelling after 2000:Proceedings of the AITES-ITA 2001 World Tunnel Congress Milan-Italy 10th-13th June 2001.Volume Ⅲ.Bologna:PArIRON EDITORE,2001:341-351.
  • 8[6]P.Gattinoni,M.Papini,L.Seesi.Geologic risk in underground works[C]//Progress in Tunnelling after 2000:Proceedings of the AITES-ITA 2001 World Tunnel Congress Milan-Italy 10th-13th 2001.Volume Ⅰ.Bologna:PATRON EDITORE,2001:309-318.
  • 9[2]Frederic L.Pellet,Time dependent Behaviour of Rock related to Underground Construction[R],ISRM Lecture Tour 2006.
  • 10[3]Pietro Lunardi.The design and construction of tunnels using the analysis of controlled defor mation in rocks and soils[J].Rocksoil S p A Piazza San Marco,2000(5).

共引文献63

同被引文献17

引证文献2

二级引证文献5

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部