大跨度“U+箱”连续梁桥的合龙施工

Closure Construction of Long-span"U+Box"Shaped Continuous Beam Bridge
在线阅读 下载PDF
导出
摘要 结合工程实际,对场地条件狭小条件下,“U+箱”形断面连续梁的合龙施工技术进行了攻关。在不改变主梁无应力状态量的情况下,根据桥梁自身荷载、跨径分布,提出了分级卸载方案。经过数值计算和施工验证,该方案操作便捷,效果可靠,有效解决了顶板开裂问题,对同类工程具有一定的借鉴意义。 Based on the engineering practice,the closure construction technology of"U+box"shaped section continuous beam under narrow site conditions has been tackled.According to the load and span distribution of the bridge itself,the grading unloading scheme is put forward without changing the unstressed state of the main girder.Through numerical calculation and construction verification,the scheme is convenient to operate,reliable in effects,and effectively solves the problem of roof cracking,which has certain reference significance for similar projects.
作者 马忠政 孙海涛 孙九春 MA Zhongzheng;SUN Haitao;SUN Jiuchun(Shanghai Shentong Metro Group Co.,Ltd.,Shanghai 201103,China;Shanghai Municipal Engineering Design Institute(Group)Co.,Ltd.,Shanghai 200092,China;Tengda Construction Group Co.,Ltd.,Shanghai 201204,China)
出处 《建筑施工》 2023年第5期944-946,共3页 Building Construction
关键词 连续梁 跨线节点桥 合龙 分级卸载 continuous beam overpass nodal bridge closure grading unload
  • 相关文献

参考文献7

二级参考文献29

共引文献58

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部