摘要
根据某隧道的实际工程地质状况,采用隧道监控量测及超前钻孔等方法,及时准确地反馈施工信息,调整施工方案,有效地指导施工,从而使施工始终处于安全可控状态。该隧道采用信息化施工方法成功地穿越长达322m的软弱破碎带。这证明了信息化施工的可行性和优越性。
According to the geological condition of areal project,by means of tunnel monitoring measurement and advanced borehole method,the accurate and prompt feedback of construction information helps to adjust the plan of construction,guides the construction and controls the project within the scope of security effectively.By using the information construction method,the topical metro tunnel has successfully crossed through the weak crushed zone of 322 meters in length,which verifies the feasibility and superiority of the construction method.
作者
赵军
周跃峰
ZHAO Jun, ZHOU Yuefeng(School of Civil and Architectural Engineering, Anyang Institute of Technology, 455000, Anyang, Chin)
出处
《城市轨道交通研究》
北大核心
2018年第6期101-104,共4页
Urban Mass Transit
基金
河南省科技计划重点公关资助项目(142102310189)
安阳工学院青年基金项目(QJJ2015021)
关键词
隧道工程
破碎带
变形量测
信息化施工
tunnel engineeling
weak crushed zone
de-formation measurement
information construction