摘要
采用不规则三角网格和有限体积方法的FVCOM模型,对山东省乳山口湾进行了潮汐电站建坝前水动力环境的现状模拟和建坝后的预测模拟,模式结果与实测数据吻合良好。在此基础上对建坝前后乳山口湾,潮位特征、流场及余流场分布情况、海湾自净能力等水文环境要素进行了对比,系统分析了乳山口湾水文动力环境要素特征以及潮汐电站建坝对乳山口水动力环境的影响。
A structured grid and finite-volume model coastal ocean model (FVCOM) were employed to simulate the hydrodynamic environment of Rushan bay at pre- and post-construction of the dam of tidal power station. The results agree well with the observation. Based on the simulation, the tide, current field, residual current field, water exchange rate between pre- and post- construction of the dam was compared to analyze the effects of the Dam on hydrodynamic environment.
出处
《海洋技术》
北大核心
2012年第3期74-78,共5页
Ocean Technology
基金
乳山口4万千瓦级潮汐电站站址勘查及预可研(GHME2010ZC08)
关键词
乳山口
水动力环境
FVCOM
潮汐电站
建坝
Rushan bay
hydrodynamic environment
FVCOM
tidal power station
construction of the dam