港珠澳大桥岛隧工程东人工岛岛隧结合部清淤施工工艺浅析 被引量:1

Desilting of foundation trench of immersed tube at the combination of eastern island and tunnel for island and tunnel project of Hong kong-Zhuhai-Macao Bridge
在线阅读 下载PDF
导出
摘要 港珠澳大桥东连香港、西接珠海、澳门,是集桥、岛、隧为一体的超大型跨海通道,岛隧工程是大桥的施工控制性工程,由沉管隧道、东西人工岛三大部分组成,其中沉管隧道是目前世界上综合难度最大的沉管隧道之一。针对港珠澳大桥岛隧工程东人工岛岛隧结合部特殊的工况条件,依据专用清淤船设备特点,制定特殊的清淤施工工艺。文章对专用清淤船的施工条件、设备特点和施工过程做介绍,分析潮流对船舶施工展布影响,制定安全合理的船舶姿态调动方式,从而确保清淤施工顺利进行;同时为今后类似施工区域狭小,水流条件复杂等作业条件下的船舶施工作业提供借鉴。 The Hong Kong-Zhuhai-Macao Bridge is connected to Hong Kong in the east and Zhuhai and Macao in the west. It is a super-large cross-sea passage integrating bridges,islands and tunnels. The island tunnel project is the construction control project of the bridge. It consists of an immersed tunnel and two artificial islands. Especially,the immersed tunnel is one of the most difficult immersed tunnels in the world. Based on special construction condition of the combination of Eastern island and tunnel in Hong kong-Zhuhai-Macao Bridge island and tunnel project,specified construction technology has been formulated by relying on the equipment characteristics of the desilting ship. In this paper,construction condition,equipment characteristics and construction process were introduced,and the influence from tidewater was also analyzed. The point was formulating equitable transfer method for ship attitude in order to guarantee that construction is completed safely. At the same time,there was some experience for construction ship at the similarity condition of regional narrow and complicated flow condition.
作者 杨秀武 何波 YANG Xiu-wu;HE Bo(CCCC Guangzhou Dredging Co. LTD. ,Guangzhou 510221,China)
出处 《水道港口》 2018年第S2期116-119,共4页 Journal of Waterway and Harbor
关键词 疏浚工程 清淤 港珠澳大桥岛隧工程 船舶姿态 desilting construction dredging combination of island and tunnel island and tunnel project of Hong kong-Zhuhai-Macao bridge ship attitude
  • 相关文献

参考文献2

二级参考文献6

  • 1中交公路规划设计院有限公司.港珠澳大桥主体工程岛隧工程施工图设计[R]. 2011.
  • 2JTS 257—2008,水运工程质量检验标准[S].
  • 3中交公路规划设计院有限公司. 港珠澳大桥主体工程岛隧工程施工图设计:沉管隧道[R]. 2011.
  • 4中交股份联合体港珠澳大桥岛隧工程第IV 工区项目经理部.港珠澳大桥岛隧工程E14 管节末端钢封门前回淤基床处置施工安全保障专项措施[R]. 2014.
  • 5中交股份联合体港珠澳大桥岛隧工程第IV 工区项目经理部.港珠澳大桥岛隧工程沉管隧道基槽清淤施工方案[R]. 2012.
  • 6郑伟.港珠澳大桥沉管隧道深基槽回淤监测与分析[J].中国港湾建设,2015,35(11):25-28. 被引量:13