上软下硬地层盾构隧道施工控制技术 被引量:1

CONSTRUCTION CONTROL TECHNOLOGY OF SHIELD TUNNEL IN UPPER SOFT AND LOWER HARD STRATUM
在线阅读 下载PDF
导出
摘要 为解决上软下硬地层中盾构施工遇到的问题,采用理论分析的方法,并结合具体工程实例,通过分析土仓压力、推力、刀盘转速和掘进速度等掘进参数,验证施工措施的合理性。结果表明在上软下硬地层中,盾构施工采取“满土仓、小推力、低转速和慢掘进”的施工控制方法,能够满足地表沉降规范要求。文中研究结果可为相似地层中盾构隧道施工提供借鉴和参考。 Combining with specific engineering examples,theoretical analysis method is applied to solve the prob⁃lems encountered in shield construction in upper-soft and lower-hard stratum,the rationality of construction mea⁃sures is verified by analyzing tunneling parameters such as soil tank pressure,thrust,cutter head speed and tunnel⁃ing speed.We propose a construction control method featuring full soil tank,small thrust,low cutter head speed,and slow shield tunneling,by which the requirements of the surface subsidence specification are satisfied.The paper may provide the reference for shield tunnel construction in similar strata.
作者 栾义浩 王旭春 罗敏鹤 刘绪壮 郝展鹏 LUAN Yihao;WANG Xuchun;LUO Minhe;LIU Xuzhuang;HAO Zhanpeng(School of Civil Engineering,Qingdao University of Technology,Shandong Qingdao 266033,China)
出处 《低温建筑技术》 2024年第1期114-118,共5页 Low Temperature Architecture Technology
关键词 上软下硬地层 盾构隧道 掘进参数 地表沉降 upper-soft and lower-hard stratum shield tunnel tunneling parameters surface subsidence
  • 相关文献

参考文献11

二级参考文献101

共引文献170

同被引文献9

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部