隧道大变形及软弱围岩支护及掘进技术研究

Research on Supporting and Driving Technology of Tunnel Large Deformation and Weak Surrounding Rock
在线阅读 下载PDF
导出
摘要 沈白铁路白山隧道穿越软弱大变形围岩地段,在初支完成后,围岩出现严重变形,多次进行初支的拆换处理,导致施工缓慢。基于软弱围岩的变形机理,提出了软弱围岩处理的理论及原则,从超前支护、掘进、初支、二衬等各环节均采取了科学有效的处理措施,确保了白山隧道穿越软弱围岩地段施工的安全、快速进行。 The Baishan Tunnel of Shen-Bai Railway passes through a section of weak and large-deformed surrounding rock.After the completion of the initial support,the surrounding rock was severely deformed.The dismantling and replacement of the initial support was carried out many times,resulting in slow construction.Based on the deformation mechanism of the weak surrounding rock,the theory and principles for the treatment of the weak surrounding rock are put forward.Scientific and effective treatment measures have been taken from the links of advanced support,excavation,primary support,and secondary lining to ensure that the Baishan Tunnel passes through the weak wall.The construction of the rock section is carried out safely and quickly.
作者 王金龙 WANG Jin-long(China Railway 12th Bureau Group No.1 Engineering Co.,Ltd.,Xi'an 710038,China)
出处 《价值工程》 2021年第36期101-103,共3页 Value Engineering
关键词 高铁隧道 软弱围岩 大变形 理论分析 措施研究 high-speed railway tunnel weak surrounding rock large deformation theoretical analysis measure research
  • 相关文献

参考文献3

二级参考文献12

共引文献24

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部