摘要
结合宁波市鄞县大道地下综合管廊的工程实例,分析研究了结合地铁建设同步实施地下综合管廊建设的必要性、可行性和适用性。通过分析可以看出:两者结合设计、同步实施必要性强,地铁车站、区间与地下综合管廊结合方案技术可行,并可节省投资,提升效益;结合方案的不同组合可适用于不同现状的城区,适用性广。
Combined with the engineering of underground utility tunnel in Ningbo City,the necessity,feasibility and applicability of the synchronized implementation of underground utility tunnel with metro construction are analyzed.Based on the analysis,the combined design and joint implementation shows a strong necessary,the integrated construction scheme of metro station,metro section and underground utility tunnel is very feasible,which can save investment,improve efficiency,and be applied to different urban areas with different combination forms.