根据晒谷坪水电站存在的问题,提出了水力机械改造措施,并通过对同水头段的模型转轮参数进行对比,提出了推荐的机组目标参数,为实现电站稳定运行、增容改造以及设备招标提供依据。
The capacity expansion renovation scheme for hydraulic machinery in Shaiguping Hydropower Plant is proposed. With a comparison of the model runner parameters under similar water head,the new unit parameters are selected,which could provide a technical basis for the following renovation work,equipment purchasing and the stable operation of the power plant.
出处
《水电与新能源》
2016年第12期13-17,共5页
Hydropower and New Energy
关键词
晒谷坪水电站
增容改造
参数选择
Shaiguping Hydropower Plant
capacity expansion renovation