矮塔斜拉桥临时固结体系模拟方案研究 被引量:3

Simulation Research into Temporary Consolidation of Extradosed Cable-Stayed Bridges
在线阅读 下载PDF
导出
摘要 当矮塔斜拉桥主梁采用悬臂法施工时,为保证桥梁的稳定性和安全性,需对主梁进行临时固结.建立4种Midas civil模型模拟某矮塔斜拉桥的临时固结体系,对不同模型的计算结果进行对比分析,从而得出与实际情况最为符合的模拟方案,为以后的临时固结体系模拟提供参考,更好地对施工过程进行指导与控制. To guarantee the stability and safety of a bridge, a temporary consolidation is of great importance to main when cantilever construction method is used in constructing an extradosed cable-stayed bridge. Four kinds of Midas models are firstly built to simulate the temporary consolidation system of a short tower cable-stayed bridge. The results ofdifferent models are, then, compared and analyzed to get a simulation scheme which is the most consistent with actualsituations. This can shed light on future simulations of temporary consolidation systems, process and controls.
出处 《南京工程学院学报(自然科学版)》 2016年第2期23-28,共6页 Journal of Nanjing Institute of Technology(Natural Science Edition)
基金 江苏省交通运输科技项目
关键词 最大悬臂状态 临时固结 桥墩 永久支座 largest cantilever state temporary consolidation pier permanent support
  • 相关文献

参考文献8

二级参考文献41

共引文献35

同被引文献15

引证文献3

二级引证文献5

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部