摘要 针对离散型生产中工艺路线不确定,工时不准确,加工中变化快,物流速度快的生产现状,提出计划期内生产的价值作为追求目标,排产不必追求任务完成的时间节点,而应制定投产的顺序,以保证企业在单位时间内实现的价值最高,即价值密度作为排产依据.确定车间的瓶颈设备之后,通过排产保证该设备前面有足够的零部件等待加工,将人力资源和设备混合排产,在动态中实现任务计划的改变、时间窗口的锁定或拒绝,兼顾了订单的重要性和交货时间,发挥出了车间设备的最大能力.每个任务的计算量仅有一次,特别适合动态中的快速排产. To solve the problems of route uncertainty, inaccuracy of work time, fast changes of the process and fast logistics in the status of discrete production process, a method is proposed that makes the value of production in plan period as the pursuit goals. The completion time node is not needed to be pursued in schedule but the production order. So that enterprise can get the highest value in unit time, namely making production scheduling based on the value density. After determining the bottleneck of workshop equipment, this method ensures that there are enough parts for" processing in front of the equipment through scheduling and mixes human resources and equipment in scheduling, making implementation of task changes and lock or refuse of time window in dynamic status. Both the importance of order and time of delivery are considered in order to make full use of the workshop equipment capacity. Each task is computed for only one time, which is especially suitable for rapid production scheduling in dynamics.
出处 《计算机系统应用》 2015年第6期1-7,共7页 Computer Systems & Applications
关键词 离散型生产 约束理论 价值密度 动态 生产计划 discrete production constraint theory value density dynamic production scheduling
  • 相关文献

参考文献12

  • 1王军强,孙树栋,王东成,杨宏安.基于约束理论的制造单元管理与控制研究[J].计算机集成制造系统,2006,12(7):1108-1116. 被引量:25
  • 2沈浩然,李爱平,刘光富.基于混合遗传算法的可重组制造系统作业计划方法[J].机电一体化,2007,13(1):9-13. 被引量:3
  • 3Chang Q. Supervisory factory control based on real-time production feedback. Journal of Manufacturing Science and Engineering, 2007, 129(3): 653-66.
  • 4Roser C, Nakano M, Tanaka M. Comparison of Bottleneck Detection Methods for AGV System. Chick PJ, Sanchez DF, Morrice DJ, eds. Simulation Conference. Proc. of the 200[3]Winter. San Diego, CA, USA. 2003. 1192-1198.
  • 5Li L, Chang Q, Ni J. Data driven bottleneck detection of manufacturing systems. International Journal of Production Research, 2009, 47(18): 5019-5036.
  • 6Biller S. Bottlenecks in Bernoulli serial lines with rework. IEEE Transactions on Automation Science&Engineering, 2010, 7(2): 208-217.
  • 7吴鸿辉,李荣贵.限制驱导式现场排程与管理技术.修订2版.台北:全华科技图书股份有限公司,2007.
  • 8诸葛景泉,孙树栋,王军强,王萌.基于约束理论和遗传算法的Job-shop调度研究[J].机械科学与技术,2010,29(11):1456-1460. 被引量:2
  • 9石小光,孙树栋,涂袁志,金玫.一种面向Job-shop的制造资源冲突消解方法[J].机械科学与技术,2011,30(12):1985-1989. 被引量:3
  • 10Louw L, Page DC. Queuing network analysis approach for estimating the sizes of the time buffers in Theory of Constaints-controlled production systems. International Journal of Production Research, 2004, 42(6): 1207-1226.