基于3G网络的大跨度连续钢系杆拱桥顶推施工监控研究 被引量:7

Monitoring of Incremental Launching Construction for Large Span Continuous Steel Arch Bridge Based on 3G Network
原文传递
导出
摘要 以淮南孔李淮河大桥右汊主航道桥为工程背景,采用有限元软件MIDAS和ANSYS对该桥顶推施工进行仿真分析,并依据理论计算制定了施工监控方案,对结构关键截面和部位进行应力和变形的监测。施工监测结合3G网络和数据采集模块,对监测数据进行了实时量测、集中采集和无线传输,实现全桥施工过程中的在线实时监测,对顶推施工进行了有效的控制和监测。理论分析与实测结果对比表明,仿真分析结果合理,基于3G网络和数据集中采集的施工监测方案可作为借鉴。 In the paper the main navigation channel bridge on the right side of Huai River Bridge in Huainan is taken as the engineering background.The finite element software Midas and the ANSYS are used to simulate and analyze the jacking construction of the bridge,and according to the theoretical calculation,the construction monitoring plan is prepared,and the stress and deformation of the structure at key sections and parts are monitored.Construction monitoring is carried out combining with 3Gnetwork and data acquisition module,and the monitoring data is real-time measured,acquired in groups and transmitted through wireless,realizing on-line real-time monitoring of the bridge construction process,and the incremental launching construction is effectively controlled and monitored.The comparisons between theoretical analysis and measured results shows that the simulation results are reasonable,and the construction monitoring scheme based on 3Gnetwork and data collection can be used as reference.
作者 倪传志 宋郁民 王成波 NI Chuan-zhi;SONG Yu-min;WANG Cheng-bo(Shanghai University of Engineering Science,Shanghai 201620,China)
出处 《公路》 北大核心 2018年第12期111-115,共5页 Highway
关键词 桥梁工程 顶推施工 仿真分析 变形监测 无线传输 3G网络 实时监测 bridge engineering incremental construction simulation analysis deformation monitoringwireless transmission 3Gnetwork real-time monitoring
  • 相关文献

参考文献8

二级参考文献65

共引文献197

同被引文献71

引证文献7

二级引证文献46

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部