摘要 隔河岩电站大坝左肩基岩加固处理,设置阻滑键、传力柱、传力洞等,为了实测加固效果,采取仪埋监测方案,根据测试结果,进行了分析。 In Geheyan hydro power plant the left dam shoulder foundation rock was reinforced and slide resistant keys,force transmission poles and force transmission cavities,etc.were constructed.In order to measure the reinforcing effects,a pre buried instrumentation scheme for monitoring was implemented.From the measuring results,analysis was made. Several questions about pre buried instrumentation and monitoring were also discussed.
作者 张清江 梁波
出处 《湖北电力》 1999年第2期14-16,共3页 Hubei Electric Power
关键词 坝肩基岩 安全监测 加固 重力拱坝 电站 施工 mother rock of dam shoulder slide resistant key instrument buried safety monitoring