110 kV内桥接线变电站普遍采用进线备自投,来进一步保证系统的安全、稳定运行及提高系统供电可靠性。对110 kV内桥接线进线备自投在现场应用中与主变保护、进线保护的配合问题进行了分析,并针对这些问题提出了改进措施,该改进措施能够解决生产和设计过程中遇到的技术问题。
Incoming line back-up self-switching equipment is universally applied in 110 kV substation with internal bridge connection for further ensuring the safety, stable operation & improving reliability of system. The coordination of above equipment with main transformer protection and incoming line protection is analyzed, and improvement measures are proposed to solve the encountered problems.
出处
《陕西电力》
2009年第6期76-78,共3页
Shanxi Electric Power
关键词
内桥接线
进线备自投
存在问题
分析
改进措施
internal bridge connection
incoming line back-up self-switching equipment
exited problem
analysis