盾构提前过站对车站施工造成的施工难点及采取的相应技术措施 被引量:5

Technical Difficulties and Measures in the Construction of Subway Station Due to Shield Machine's Crossing Station
在线阅读 下载PDF
导出
摘要 通过对北京地铁四号线圆明园车站盾构过站施工的总结及分析,着重从调整盾构掘进轴线、变更围护结构形式、车站端头加固等几方面介绍盾构在车站未施工前直接过站对车站的后期施工造成的施工难点及为保证车站施工所采取的相应技术措施。 Based on the analysis of the shield machine's crossing Yuanmingyuan station on metro line No.4 in Beijing, this paper discusses mainly the adjustment of the shield axis, the change of support structure and the reinforcement of the ends of station. And, the technical difficulties in the construction of subway station are researched because the shield machine crosses the station before the station begins to construct. At last, the technical measures are presented in this paper.
作者 陈刚 王二平
出处 《隧道建设》 2007年第S2期555-558,共4页 Tunnel Construction
关键词 盾构提前过站 难点 技术措施 shield machine's crossing station difficulty technique measure
  • 相关文献

同被引文献23

引证文献5

二级引证文献29

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部