介绍了我国自主生产的首台1 000MW汽轮发电机组的特点,从安装、调试方面详细论述了在发电机严重滞后的情况下,汽轮发电机组本体安装工作的组织和管理,论证了在发电机不就位的情况下进行汽轮机扣缸的可行性。
The feature of the first domestic turbo-generalor was described. The organization and management of turbo- generator erection and commission while the generator delivery was lagged seriously were expounded in detail. The feasibility of condenser covering while Ihe generator is not in location was proofed, and the measures must be adopted were given too.