摘要
结合湖南省汉寿沅水大桥工程实例,介绍了100 m悬浇箱梁施工工艺的改进措施,提出了具体的施工步骤,以充分利用已有设备和材料,提高设备和材料的周转和利用率,从而达到加快施工进度和降低施工成本的目的。
Combined with the Hanshou Yuanshui Bridge engineering example, the improved measures of 100 m suspending cast box beam construction technology were introduced and the specific construction procedure was proposed so as to make full use of the existing equipments and materials and enhance the turnover and the availability of equipments and materials, which can accelerate construction progress and reduce the construction cost.
出处
《山西建筑》
2008年第22期129-131,共3页
Shanxi Architecture
关键词
悬浇箱梁
挂篮
施工工艺
改进措施
suspending cast box beam, traveling carriage, construction technology, improved measures