北京市北护城河新建松林闸深基坑工程,受周边复杂环境限制,原设计放坡开挖方案难以实施,本文结合工程实际,提出了支护优化方案,并从各方面对原方案和优化方案进行了对比,结果表明优化方案的合理性。
The excavation of Beijing Moat north part Songlin Gate deep foundation pit is restricted by complicated surrounding conditions. The previous construction scheme of slope excavation is hard to be performed. Based on the actual surrounding conditions, this article presents an optimized supporting system scheme. It is indicated that the optimized scheme is more reasonable by comparison of the previous and optimized supporting system.