摘要
对松花江大顶子山航电枢纽工程灯泡贯流式水轮发电机组主轴组装、安装及轴线调整工艺进行分析,同时计算出了主轴在安装过程中主要参数的调整量,对其它类似电站具有借鉴意义。
The technology for main shaft assembling,installation and axis adjustment of the bulb turbine and generator units of Dadingzishan Navigation and Hydropower Project is briefly analyzed herein;in which the main parameters of the adjustments for the installation of the main shafts are calculated,which can be provided as reference for the other similar projects.
出处
《水利水电技术》
CSCD
北大核心
2008年第12期78-80,共3页
Water Resources and Hydropower Engineering
关键词
灯泡贯流式水轮发电机组
主轴组装
安装
轴线调整
大顶子山航电枢纽工程
bulb turbine and generator unit
main shaft assembling
installation
axis adjustment
Dadingzishan Navigation and Hydropower Project