摘要
研究目的:为了解决客运专线架桥机通过隧道架梁施工的技术难题。本文结合石太客运专线Z8标段工程中架桥机过隧道架设大吨位箱梁实例,分析了架桥机过隧道架梁的影响因素和必要性。通过重点介绍TLJ900型辅助下导梁式架桥机进隧道口时末孔箱梁以及出隧道口首孔箱梁的施工方法、施工步骤,总结出一套宝贵的施工技术。研究结果:通过TLJ900型架桥机过隧道架梁施工技术总结,体现了TLJ900型架桥机在过隧道箱梁架设过程中的先进性、灵活性和安全性。
Research purposes:Taking erecting heavy-tonnage box girder with bridge girder erecting machine in Bidding Z8 section of Shijiazhuang-Taiyuan Railway Passenger Dedicated Line as an example,the analyses of the influencing factors on and necessity of erecting girder with bridge girder erecting machine while passing through tunnel are made.The tough technical problem of erecting girder with bridge girder erecting machine TLJ900 while passing through tunnel of passenger dedicated line is overcome by adopting the...
出处
《铁道工程学报》
EI
北大核心
2007年第S1期269-273,共5页
Journal of Railway Engineering Society
关键词
客运专线
TLJ900型架桥机
通过隧道
架梁
railway passenger dedicated line
Bridge Girder Erecting Machine TLJ900
passing through tunnel
girder erection